Hinkal Flyover deadline: Enforce stringent clauses

Sir, Apropos the news item “Hinkal Flyover not before Dasara” (SOM dated Sept.17), we find that most of the works executed by Mysuru Urban Development Authority (MUDA) or Mysuru City Corporation (MCC)…

By Author
Published September 19, 2018 · 1 min read
hinkal flyover deadline: enfor

Sir, Apropos the news item “Hinkal Flyover not before Dasara” (SOM dated Sept.17), we find that most of the works executed by Mysuru Urban Development Authority (MUDA) or Mysuru City Corporation (MCC) gets extended much beyond the stipulated deadline to complete the projects. May be owing to biased contract agreement terms favouring the contractors, works like Town Hall parking and Hinkal Flyover are not getting executed within the stipulated time period. When the tax-payers’ money is involved in financing these projects, it is the duty and the responsibility of the bureaucrats to draft stringent  terms and conditions in the contracts. Stipulated time of completion and penal clause in case of failure to complete  the project within the stipulated time should be clearly mentioned.  MUDA or MCC should be able to  initiate stringent action against the  defaulting contractors, based on these terms and conditions. Projects like Raja Marga and construction of Sri Jayadeva Institute of Cardiovascular Sciences and Research Centre were not executed within the stipulated period  and instead of applying penal clause for the delay, the contractors  were awarded escalation cost over and above the contract amount. To save money, most of the contractors employ less number of labour and then go on extending the contract period claiming escalation costs. The authorities concerned should strictly draft  penal clauses and also apply these  penal clauses when there is an unreasonable delay in the execution of projects using public funds.

- K. Chandrahas, Mysuru, 18.9.2018

Continue reading

From the Voice of The Reader desk
photo
Voice of The Reader

Unlevelled pit posing danger to motorists

15 Jul 2026 · 1 min read
photo
Voice of The Reader

Garbage dumping destroying our neighbourhood

14 Jul 2026 · 1 min read