Project nearing completion with 7-km cabling pending; MP visits work site
Mysore/Mysuru: Over three months after launching the project to lay underground insulated wires for the street-lights on the Ring Road, over 78-km of the project has been completed and only seven kilometres of cabling is to be done. All the works will be completed by Dec. 1 and the lights will finally glow from that date. After much delays, dilly-dallying on allotment of funds and shifting responsibilities, the project was launched on Aug. 15, 2022.