Mysuru-Chamarajanagar line electrification: Airports Authority issues NOC after years of delay

Mysore/Mysuru: After years of deadlock, the South Western Railway has finally overcome a long-pending technical hurdle in electrifying the Mysuru-Chamarajanagar railway line. The Airports Authority of India (AAI) has issued the long-awaited…

By Author
Published July 2, 2025 · 2 min read
mysuru-chamarajanagar line ele

Mysore/Mysuru: After years of deadlock, the South Western Railway has finally overcome a long-pending technical hurdle in electrifying the Mysuru-Chamarajanagar railway line. The Airports Authority of India (AAI) has issued the long-awaited No Objection Certificate (NOC), paving the way for full electrification of the route.

A critical 1.4-km stretch near Mysore Airport had remained unelectrified due to its close proximity to the Airport runway, which raised safety and navigational concerns.

Continue reading

From the News desk
photo
News

Mysuru to get Township soon?

15 Jul 2026 · 4 min read
photo
News

MLC demands immediate appointment of MDA Commr.

15 Jul 2026 · 1 min read