Mysore/Mysuru: The restoration works of the part of the fort wall of Mysore Palace has been completed. Following copious rainfall in the city last year, seven foot tall fort wall to the left of Kote Maramma Temple towards Varaha Gate had collapsed 20 metre wide on Oct. 18, 2022. The restoration works were launched on Oct. 25 and have been completed recently.
Taking into cognisance the heritage significance of the structure, Mysore Palace Board had called for an e-tender for the repair works. The dilapidated condition of fort wall had been identified in three places, totalling 50 metres length and the tender had been invited at an estimated cost of Rs. 39.6 lakh. The wall is restored using the construction materials like lime, mortar and stone to redo the structure.